Exterior Construction Photos

1/23/06 Site cleared

2/6/06 Site graded

2/9/06 Foundation trenches have been dug

2/10/06 Foundation poured

2/23/06
Clock pier footings poured, fountain pier footings formed

3/06/06 Block laying underway

3/06/06 More block, clock pier forms being placed

3/13/06 More block, water drain excavation starting

3/16/06 Steel supports up

3/16/06 Clock and fountain piers poured

3/21/06

3/24/06

3/30/06

4/05/06

4/10/06

4/13/06 The floor is poured

4/14/06

4/20/06

4/24/06

4/27/06 Roof work

5/09/06 More roof work

5/12/06

5/26/06

6/08/06

7/03/06 HVAC unit pads being poured

7/13/06

7/20/06

7/31/06

8/01/06

8/03/06

8/11/06

8/15/06